Quick Answer
Select a construction contractor by evaluating capability against the actual project, not the lowest preliminary price or the loudest project announcement. A sound procurement process sets a consistent scope, checks experience and resources, tests the proposed programme, defines quality responsibilities and records how changes, defects and commissioning will be managed.
What matters most
A comparable tender starts with the same design documents, scope, assumptions and response format for every bidder.
Verify similar delivered work, staffing, subcontractors and financial or contractual capacity using current evidence.
Review methodology, quality management, safety, interfaces and programme realism together with price.
Define change control and claims procedures before work begins.
AI Tower's CSCEC news has a different owner URL; this article focuses on buyer-side contractor selection.
Stage 01
Write a scope that bidders can actually price
An invitation to tender that says only 'construct the building' will produce offers that cannot be compared fairly. Prepare design drawings at an appropriate maturity, a schedule of deliverables, technical specifications, approved assumptions, programme constraints, site conditions and clear statements about whether the contractor designs, builds or coordinates each element. Identify provisional sums and exclusions deliberately.
For mixed-use projects, ask who controls civil, structural, MEP, fire protection, fit-out, landscape and specialist supplier interfaces. One missing responsibility can become a costly change order later. Use a common response template for every bidder so scope gaps are visible before award.
Questions to resolve
- Issue a common drawing/specification register and pricing template.
- List employer-provided work and assumptions explicitly.
- Ask each bidder to identify qualifications and exclusions separately.
Stage 02
Verify relevant delivery evidence and the actual team
A broad portfolio is useful context, but it does not prove that the bidder has delivered an equivalent technical project under similar conditions. Request named, dated reference projects, the contractor's exact role, a realistic staff organization chart, proposed key subcontractors and documented quality or safety records suitable for independent review. Where sensible, speak to former clients and visit comparable work with permission.
Do not confuse developer, general contractor, specialist subcontractor, consultant and technology partner roles. For example, AIG's 2026 AI Tower communications identify CSCEC as the appointed main contractor and Honeywell for the smart-building technology layer. Those are project role statements, not guarantees of outcome or evidence that AIG itself performed every trade.
Questions to resolve
- Check actual contract role and relevant scope on past projects.
- Meet the proposed site and project leadership, not just the sales team.
- Request verifiable registrations, insurance and any role-specific approvals.
Stage 03
Stress-test the construction programme and commercial terms
A programme needs more than a target end date. Ask about design release dates, long-lead materials, access, inspections, utilities, coordination milestones, float and realistic testing and handover periods. Compare critical path assumptions across bids and ask for a resourcing plan that supports the schedule. A promise of exceptional speed without evidence deserves scrutiny rather than bonus points.
Review the payment mechanism, variation process, escalation treatment, interim certifications, defect responsibilities and dispute route with a qualified contract adviser. Keep provisional allowances visible instead of burying them in attractive headline prices. The best bid for your project may not be the smallest number if other material obligations are excluded.
Questions to resolve
- Require a sequence-level programme with stated resource assumptions.
- Separate fixed price, provisional sums, allowances and owner-supplied items.
- Agree variation approval, delay notices and dispute procedures before signing.
Stage 04
Make quality and handover inspectable
Ask for a project-specific inspection and test plan, material approval procedure, mockups where relevant, independent checks, nonconformance handling and traceable records. Hold-points should be placed before work becomes concealed. For technical systems, handover should incorporate commissioning evidence, training and operation documentation, not just a completion certificate.
AIG's own published portfolio provides useful context about regional development, including Burj Al Madina in Al Bayda and residential projects in Benghazi, Libya, plus its AI Tower development in Egypt. Those records identify projects and locations; they should not be treated as independent verification of contract values, delivery percentages or outcome metrics absent supporting documentation.
Questions to resolve
- Define acceptance tests and responsibility for defects clearly.
- Track approvals, change requests, inspections and nonconformances centrally.
- Request a final as-built, warranty, training and asset-information pack.
Direct AIG Contact
Discuss a construction or development brief
Share your city, project type, stage and scope. Ask AIG to direct you to the relevant development or construction contact for an evidence-led discussion.
First-party Context
Portfolio and role evidence from AIG

The AIG project catalog lists Burj Al Madina in Al Bayda, Libya, residential development in Benghazi and a New Capital development. Separately, the live AI Tower material identifies CSCEC as its appointed main contractor in August 2026. This is a real portfolio and role context, not an assertion that every project is completed or delivered by the same contractor.
Practical checklist
Use these points to structure a meeting or tender enquiry. They are not a substitute for licensed local design, legal, health or engineering review.
Questions frequently raised by project teams
Should I award a contract to the lowest bidder?
Only after confirming every major bid prices the same scope and meets the project's safety, quality, delivery and contractual needs. The lowest headline number can hide exclusions.
Does working with a famous contractor guarantee a delivery date?
No. Verify the project-specific contract, programme, resourcing, risks, site conditions and evidence of progress rather than drawing a guarantee from reputation.
What document prevents the most tender misunderstandings?
No one document is sufficient, but a coordinated scope of work, specification, drawings and responsibility matrix provide the foundation for a fair comparison.
Sources & further reading
Company project statements are based on AIG's own published material. Technical standards may require purchase and do not replace locally applicable approvals.